Please read all installation instructions carefully before
proceeding. Wiring diagrams are located in the
appendix of this manual. Use the BTU Meter Certicate
of Calibration (C of C) to verify that the Specied
Installation & Operating Parameters match the actual
conditions at the location where the meter is installed.
A worksheet for checking off these steps and recording
measured values is located on the following page.
4.7 COMMISSIONING
Upon initial installation, it is strongly recommended that both the System-10 and its associated ow
meter be commissioned to ensure that they are properly installed and functioning correctly. This
process involves verifying the mechanical installation, measuring ow and temperature signals and
then comparing these measurements to the specied installation and operating parameters listed on the
certicate of calibration provided with the meter. The data collected during this initial commissioning
process will then serve as baseline data for periodic revalidation of the meter operation.
COMMISSIONING PROCEDURE - ONICON BTU METERS