Please read all installation instructions carefully before
proceeding. Wiring diagrams are located in the
appendix of this manual. Use the BTU Meter Certicate
of Calibration (C of C) to verify that the Specied
Installation & Operating Parameters match the actual
conditions at the location where the meter is installed.
A worksheet for checking off these steps and recording
measured values is located on the following page.
4.7 COMMISSIONING
Upon initial installation, it is strongly recommended that both the System-10 and its associated ow
meter be commissioned to ensure that they are properly installed and functioning correctly. This
process involves verifying the mechanical installation, measuring ow and temperature signals and
then comparing these measurements to the specied installation and operating parameters listed on the
certicate of calibration provided with the meter. The data collected during this initial commissioning
process will then serve as baseline data for periodic revalidation of the meter operation.
COMMISSIONING PROCEDURE - ONICON BTU METERS