1
1451 Belcher Road South, Largo, FL 33773 • USA
• Tel +1 (727) 447-6140 • Fax (727) 442-5699 •
[email protected]F-2600 & F-2700 Vortex Flow Meter Manual 02/15 - 0808-7 / 19204 Page 22
2.2.1 Wafer-Style Flow Meter Installation
Install the wafer-style meter between two conventional pipe anges of the same nominal
size as the ow meter. If the process uid is a liquid, make sure the meter is located where
the pipe is always full. This may require locating the meter at a low point in the piping
system. Note: Vortex ow meters are not suitable for two-phase ows (i.e., liquid and gas
mixtures). For horizontal pipelines having a process temperature above 300° F, mount the
meter at a 45 or 90 angle to avoid overheating the electronics enclosure. To adjust the
viewing angle of the enclosure or display/keypad, see page 34 and 35.
Figure 6. Wafer-Style Flow Meter Installation
When installing the meter make sure the section marked with a ow arrow is positioned
upstream of the outlet, with the arrow head pointing in the direction of ow. (The mark
is on the wafer adjacent to the enclosure mounting neck.) This ensures that the sensor
head is positioned downstream of the vortex shedder bar and is correctly aligned to the
ow. Installing the meter opposite this direction will result in completely inaccurate ow
measurement. To install the meter:
1. Conrm that the installation site meets the required minimum upstream and
downstream pipe diameters. Turn off the ow of process gas, liquid or steam. Verify
that the line is not pressurized.
2. Insert the studs for the bottom side of the meter body between the pipe anges. Place
the wafer-style meter body between the anges with the end stamped with a ow arrow
on the upstream side, with the arrow head pointing in the direction of ow. Center the
meter body inside the diameter with respect to the inside diameter of the adjoining
piping.
3. Position the gasket material between the mating surfaces. Make sure both gaskets are
smooth and even with no gasket material extending into the ow prole. Obstructions
in the pipeline will disturb the ow and cause inaccurate measurements.
4. Place the remaining studs between the pipe anges. Tighten the nuts in the sequence
shown in Figure 5. Check for leaks after tightening the ange bolts.
CAUTION
When using toxic or corrosive gases, purge the line with inert gas for a minimum of four hours at
full gas ow before installing the ow meter.